AUGUST 2014:
TURBINE DELIVERY ROUTE TO BE TESTED

The turbine delivery route to Woolley Hill Wind Farm will be tested on Tuesday 19th August. A single low loader will travel from Immingham Docks to site as a 'dry run' to check that there will be no delays in bringing the turbine components to the wind farm in October. As the route follows the A14, there should be no disruption to local people during this test or the actual deliveries. A newsletter advising of delivery times and the approved route will be circulated to local people in the coming weeks.