Woolley Hill Wind Farm is located in Ellington, Cambridgeshire.

The wind farm was granted planning consent in March 2012 and comprises four turbines, measuring 130.5m high to the tip of the blade.

Construction work began in March 2014 with turbine deliveries taking place in summer 2014. All four Nordex turbines were erected by November 2014.

Woolley Hill Wind Farm became fully operational in March 2015 triggering a community benefits package worth £50,000 per year.